Design and construction of the CEPSA Service Areas/Petrol Station WTP and WWTP in Lançada – IC32

Timeline: 2011/2012



In this project, TEKBOX assumed responsibility in two phases:

Phase 1 – Engineering Services
Definition of technical solutions for WTP and WWTP, hydraulic dimensioning and design of the treatment installation – Only the engineering base existed in terms of water treatment, it was necessary to carry out the whole design during the construction period;

Phase 2 – Technical services – Construction Management
Technical services and construction management for the installation of the electromechanical equipment of the WTP and WWTP, including the execution of all piping, electrical circuits, instrumentation and equipment installation (pumps, filters, aeration system, dewatering, probes, controllers and electrical box);





Subscribe to our newsletter